Important Property Notices

The following Notices Below are for complexes that have current upcoming or ongoing construction/repairs at the complex or property.

For Addtional questions or concerns please email Knutsonreservations@gmail.com

Kona Makai

Starting July 22nd Kona Makai will be starting the exterior painting project on Building 4.

Currently they are estimating between 1.5 - 2 Months to complete each building for this work. 

Their current order for the painting of the  buildings mentioned below with the possible affected dates. 

Building 4 7/22 - 9-22  

Building 5 9/22 - 11/22 

Building 3 11/22 - 1/22

The painting and spalling contractor has agreed to take a break from work for Ironman and the Christmas holidays. Work will stop from October 21st-29th for Ironman. Work will stop from December 23rd- January 3rd for the Holidays  

All dates are subject to change and Knutson & Associates has no say or control in if dates are changed. Dates are given by the complex's hired painting vendor.   

The mentioned work will be affecting access to units at possible given times between the work being done on the building. Kona Makai will be sending notices of more specific dates that access will be affected between work hours. We unfortunately cannot provide any given dates for this. Other areas such as lanai access will be affected during times as well. Furthermore the AC will also not be allowed during specific times/dates when the work is going on.  

Noise and obstructed views are also to be expected between the dates mentioned.

The contractor plans on beginning spalling repairs on building 2 on September 9th , 2024 at 8:00 am. They plan to set up a scaffold at the oceanside end of the building and they will begin work on the column supporting landings in the stairwell. As they proceed, they will be working on leading edges of lanais on both sides of the building, windowsills, walls, and stairs throughout the building. When building 2 is complete they plan on moving to building 1 and then building 6.

 

 

Keauhou Kona Surf & Racquet Club 

 Townhome Oceanfront painting beginning May 19, 2025.  

The painting will begin at unit 176  and continue through to 199 and then finish with Townhome building 1-5.

The painting will only be for the oceanfront side of the townhomes. 

Please see townhomes schedule below for the affected dates. 

 

Townhomes 176-179 May 19- May 27

Townhomes 180-183 May 28- Jun 12

Townhomes 184-187 Jun 13 – Jun 30

Townhomes 188-189 Jul 1- Jul 8

Townhomes 190-195 Jul 9 – Aug 1

Townhomes 196-199 Aug 4 – Aug 19

Townhomes 1-5 Aug 20 – Sep 9

 

 

Casa De Emdeko

GARDEN POOL RENOVATION & CLOSURE

The garden pool has been scheduled for renovation beginning Monday, February 3, 2025. Barring any unforeseen issues, the pool is expected to be closed for approximately 6 weeks. Updates regarding the reopening will be provided as the project progresses.

The Ocean side pool will remain open during this work. 

 

 

 

Malia Kai 

-The complex will be doing repairs for the asphalt in the common areas. They will be blocking off areas they will be working in. 

The work will be happening from April 7th 2025 - April 15th 2025