Important Property Notices

The following Notices Below are for complexes that have current upcoming or ongoing construction/repairs at the complex or property.

For Addtional questions or concerns please email Knutsonreservations@gmail.com

Kona Makai

Starting July 22nd Kona Makai will be starting the exterior painting project on Building 4.

Currently they are estimating between 1.5 - 2 Months to complete each building for this work. 

Their current order for the painting of the  buildings mentioned below with the possible affected dates. 

Building 4 7/22 - 9-22  

Building 5 9/22 - 11/22 

Building 3 11/22 - 1/22

The painting and spalling contractor has agreed to take a break from work for Ironman and the Christmas holidays. Work will stop from October 21st-29th for Ironman. Work will stop from December 23rd- January 3rd for the Holidays  

All dates are subject to change and Knutson & Associates has no say or control in if dates are changed. Dates are given by the complex's hired painting vendor.   

The mentioned work will be affecting access to units at possible given times between the work being done on the building. Kona Makai will be sending notices of more specific dates that access will be affected between work hours. We unfortunately cannot provide any given dates for this. Other areas such as lanai access will be affected during times as well. Furthermore the AC will also not be allowed during specific times/dates when the work is going on.  

Noise and obstructed views are also to be expected between the dates mentioned.

The contractor plans on beginning spalling repairs on building 2 on September 9th , 2024 at 8:00 am. They plan to set up a scaffold at the oceanside end of the building and they will begin work on the column supporting landings in the stairwell. As they proceed, they will be working on leading edges of lanais on both sides of the building, windowsills, walls, and stairs throughout the building. When building 2 is complete they plan on moving to building 1 and then building 6.

 

 

Kona Pacific

 -The resealing and re-striping will start with the Walua Rd. entrance, B building tunnel, Visitor Parking and the Fire Lane Monday, February 10th and Tuesday, February 11th. Please use the D building tunnel and Kuakini driveway for ingress and egress. The Walua Rd. stairs and sidewalk will be open. The Kuakini Hwy. Gate will remain open during this time for those who do not have a gate opener.

-The resealing and re-striping will continue with the Outside parking lot, D building tunnel and driveway out to Kuakini Hwy. Wednesday, February 12th and Thursday, February 13th. There will be a small strip on the North side of the driveway to the E building parking garage for foot traffic. There is a back stairwell for entering the buildings.

 

SEA VILLAGE 

-The pool at sea village will be closed to clean and reseal the flagstone deck as well as replace the expansion joints. 

The pool will be closed from NOVEMBER 11TH - NOVEMBER 16TH 

Malia Kai 

-The complex will be doing repairs for the asphalt in the common areas. They will be blocking off areas they will be working in. 

The work will be happening from April 7th 2025 - April 15th 2025